One-piece flow assembly line

Switch from bay build assembly to a paced one-piece flow line (IT)

Project description

  • Conversion of the existing bay build assembly into a paced one-piece flow assembly line with 12 workstations

  • Fixed cycle time of 8 minutes and standardized processes through work instructions

  • Integration of the entire material flow and logistics into a Kanban system for controlled material supply

  • Reduction and elimination of intermediate buffers to cut WIP and lead times and save floor space

  • New line layout including conveyor technology and building services adjustments (electrical, data and compressed air connections)

Activities

  • Project management

  • Layout, detailed and execution planning

  • Cost, time and quality management

  • Coordination of all trades and cross-departmental contact for internal implementation

  • Installation supervision and commissioning during ongoing operations

  • Preparation of status reports and minutes on project progress